        Unit-1 of Philippines Puting Bato 1x135MW Coal-Fired Power Plant Project Finished the Reliability Test Run Successfully

        Source : Author : Date:2014-10-27【Font:B M S


        At 17:00 on Oct. 27, Unit-1 of Philippines Puting Bato 1x135MW Coal-Fired Power Plant Project contracted by CNTIC finished the reliability test run successfully. The Owner, the contractor and CNTIC signed the test documents.